SOP Compliance Checks
-
-
-
-
- | Rule |
- Status |
- Details |
-
-
-
- {compliance.map((c, idx) => (
-
- | {c.rule} |
-
-
- {c.status}
-
- |
- {c.detail} |
-
- ))}
- {compliance.length === 0 && (
-
- | No compliance checks available. |
-
- )}
-
-
+
Suggested Decisions / Insights for the Changeover event (Illustrative)
+
+
+
Date
+
09-06-2025
+
Time
+
13:00 Hrs
+
Type
+
Flowchannel Changeover
+
+
Events for Attention and Improvement
+
+ - Idleness of 15 mins noticed during overall tool changeover operation. Operators to be trained accordingly.
+ - Incoming material was not kept nearby to the stock feeder before line stop. 6 mins delayed and Operators to be trained accordingly.
+ - Extruder head not opened within the std time. Auto screw reverse rotation logic to be re-validated.
+ - Operator found not in place at the right time during stock feeding operation. 5 mins delayed feeding of upper and middle barrels.
+
+
+
Events that Turned-out to be Best
+
+ - Sheetout of removed stock is carried out within 10 mins - To be followed every time
+ - All operators were complied to their adherence to PPEs, SOPs and tooling arrangements - To be followed every time
+ - Dual barrel cleanout carried out - 12 mins saved
+ - Incoming recipe was downloaded at the right time - To be followed every time
+